ConocoPhillips Australia's Environment Plan was accepted by Australia’s independent regulator, the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), in February 2025.

  • Seabed surveys commenced in April 2025.
  • Pre-lay of anchor and mooring chains is expected to be deployed by a vessel at Essington-1 in mid September 2025 and at Charlemont-1 between September and November 2025.
  • Essington-1 drilling is expected to start mid October 2025.
  • Charlemont-1 drilling is expected to start between November and December 2025.
  • The Transocean Equinox rig and support vessels are scheduled to transit to Essington-1 in October 2025 ahead of drilling the first well and then move to Charlemont-1 later in the year.

If you are a commercial marine user who has been affected by the Otway Exploration Drilling Program, you may be eligible for compensation for displacement, loss of catch, or fishing gear loss or damage.


The Regia MSS Environment Plan is currently under assessment with Australia's independent regulator, the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA).